What happens after a barrier fails
Victorian regulations give inspectors two paths when a barrier doesn’t comply. If it can be made compliant, the inspector can issue a written notice setting out what you must do, a deadline of up to 60 days and the re-inspection date. If the barrier still isn’t compliant at re-inspection but good progress has been made, a further seven days may be allowed.
In some situations, the inspector must issue a certificate of barrier non-compliance (Form 24) straight away. The inspector lodges it with council and gives you a copy. Council will contact you and a fee applies. The issues that trigger it include the following.
- A significant and immediate risk to life
- The barrier can’t be made compliant within 60 days
- A gate or door can be opened by someone unable to reach its release
- A gate or door in the barrier can’t completely close
After that, the municipal building surveyor may issue a barrier improvement notice with a deadline to fix the barrier. Missing deadlines can lead to fines.